Midway Road (County Road 712) Widening Projects
District Office
Steven C. Braun, P.E.
District Four Secretary
3400 W Commercial Blvd
Fort Lauderdale, FL 33309
Tel: 866-336-8435
Fax: 954-777-4528
Additional Contacts
Staff Directory
Welcome
The Florida Department of Transportation (FDOT) District Four will construct about 1.5 miles of Midway Road (CR 712) in St. Lucie County. The project will be completed in two segments:
1.) Glades Cut-Off Road to Jenkins Road (231440-4) - IN DESIGN
2.) Jenkins Road to Selvitz Road (231440-5) - IN CONSTRUCTION
The project limits are shown on the location map below. The projects widen the existing two-lane roadway to a four-lane divided road, inclusive of 7-foot buffered bike lanes in both directions. In addition, the project will include a 12-foot bicycle / pedestrian path on the south side of the road, and a 6-foot sidewalk along the north. The project improves safety and allows opportunities for pedestrian, bicycle, and transit facilities. The project includes the replacement of the existing bridge over Florida's Turnpike.
Working with the key stakeholders: St. Lucie County, St. Lucie Transportation Planning Organization (TPO), Florida's Turnpike Enterprise (FTE), the scope of the project has expanded to include a new partial interchange with Florida's Turnpike. The design of the new partial interchange (FPID: 451858-1) includes a northbound off-ramp, and southbound on-ramp. The partial interchange will be constructed in conjunction with the Midway Road segment from Glades Cut-Off Road to Jenkins Road (231440-4).
The Midway Road project will enhance connectivity to Florida's Turnpike Mainline through the construction of a northbound off-ramp and a southbound on-ramp. For more information about the Florida Turnpike project, please visit www.midwayramps.com.
The Midway Road Project (231440-4) has been identified as a congestion relief project (number 18) under Governor DeSantis's Moving Florida Forward Infrastructure Initiative helping to secure and advance construction funding. Please visit www.FDOT.gov/movingfloridaforward for more information.
Click on the various project resources for information about the design process, future public meetings, the project schedule, and information on how to contact FDOT's project manager.
Project At-A-Glance
District
Four
Design Start Date
Design started in February 2017.
Jenkins Road to Selvitz Road
FIN: 231440-5-52-01
Design
Complete
Construction Start Date
April 1, 2024
Anticipated Completion Date
Fall 2026
Construction Cost Estimate
$24 million
Glades Cut-Off Road to Jenkins Road
FIN: 231440-4-52-01
Design Completion
Design began in of Winter 2023 and is anticipated to be completed in Fall of 2026
Construction Start Date
Summer 2027
Anticipated Completion Date
Winter 2029/30
Construction Cost Estimate
$50.4 Million
Consultant
Adurra Group, Inc.
Project Manager
James Hughes, PE
Click here to view the project location in a larger map
Midway Road/County Road (CR) 712 Project
Financial Project IDS: 231440-4-52-01; 231440-5-52-01
ETDM No.: 14177
FIN: 231440-4-52-01
Glades Cutoff Road to Jenkins Road
FIN: 231440-5-52-01
Jenkins Road to Selvitz Road
FIN: 451858-1-52-01
Midway Road at Florida's Turnpike Partial Interchange
www.midwayramps.com